Hyde Park Stadium Project
HYDE PARK STADIUM
PROJECT SPECIFICATIONS
MIGUEL DIAS COSTA
Anglia Ruskin College London
2019/2020
This case research was ready by Miguel Dias Costa.
It’s a fictional case research aimed toward serving to college students
perceive the complexities of creating venture
administration options.
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
1 | P a g e
Hyde Park Stadium
The Mayor of London has determined to approve a proposal to construct a brand new venue to host mega occasions in
Hyde Park. As a result of particular attribute of the venture and to the positioning restrictions the development has
to observe some very particular specs. The brand new venue can be named Hyde Park Stadium. The venture
is because of begin in November 1st, 2019 and be accomplished no later than the 2nd of April 2022.
The development will comprehend a number of phases. Among the works can be carried out on website and others
will solely encompass the assemblage of the structural components and roofing (see Desk 1).
To make sure that there can be no useless durations, these works to be carried out off website must be ordered
and acquired on time.
The overall length of every one of many phases depends upon labour to be allotted (see Desk 2). Nevertheless,
the scale of the workforce may also have penalties on the gear to make use of, which signifies that prices
associates with every workforce usually are not immediately proportional with its dimension (see Desk three).
The requirements of manufacturing for every exercise are introduced in Desk 2.
Work pressure for the venture could be employed both regionally (London) or internationally (Dublin and Mumbai).
The out there workforce is introduced on Desk four.
Labour prices is introduced in Desk 5. The transportation prices is introduced in Desk 6.
Project Constraints:
1. There are three teams of potential employees to do the works. The unitary price is totally different as every
group represents totally different stage of qualifications and a unique origin by way of location. This
state of affairs is as a result of lack of extremely certified employees in London.
2. The degrees of qualification of the employees (L1 to L4) doesn’t permit any swap. That’s, a L2 employee
can’t carry out the work of a L1. And the identical applies to L3 and L4.
three. The employees will arrive immediately from their residence nation in the future forward of their working schedule.
The transportation price is supported by the Contractor.
four. The gear wanted depends upon the variety of employees and the usual of building (see
Desk three).
5. Throughout the time of labor, all employees can be hosted in a resort in London and all bills can be
supported by the Contractor.
6. The CEO is conscient of the chance of not having the development concluded earlier than the deadline.
Due to this fact, he has established a bonus for earlier completion of the venture. This bonus can be
awarded to the members of the Project Administration Crew (see Desk eight).
7. All employees are solely allowed to work eight hours per day and 5 days per week. Nevertheless, if at any
additional time is required, the price of the employee will enhance in accordance with Desk 7.
Moreover, the next day can be taken off as a strategy to decrease the workload and guarantee
high quality in building works.
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
2 | P a g e
eight. If any employee is allotted for a interval of lower than eight hours per day nonetheless he/she can be paid eight
hours.
9. Time for travelling is paid on the regular charge. The variety of days inbound and outbound, as
properly as its prices, is introduced in Desk 6.
10. All employees can be paid in response to the class (see Desk 5).
Questions:
1. Develop the venture actions and price primarily based on the earlier specs and constraints,
contemplating that:
a. The target is to finish the method with the least potential price.
b. The target is to finish the venture throughout the least potential timing.
c. The target is to make sure that your entire building course of will result in the best
potential high quality.
2. For every answer you must clearly sate your assumptions and selections.
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
three | P a g e
Desk 1
Development Schedule
Notes:
1. Manufacturing time could be shortened by 2 weeks with an additional price of 30% on
primary price).
2. Manufacturing time could be shortened by three weeks with an additional price of 50% on
primary price).
three. Manufacturing time could be shortened by 1 week with an additional price of 70% on primary
price).
Desk 2
Development Requirements
The place:
1. Process Period: Represents the variety of working days allotted for the duty.
2. Process Content material: Represents the works to be carried out on that job
three. Process Predecessors: Characterize the duty that must be accomplished earlier than the duties begins.
four. Labour in Days: Represents the variety of man-days for every job an for every employee stage.
5. Every week will comprehend 5 working days of eight hours. No further hours or further days are allowed.
Exercise Web site Off Web site Remarks
Web site Levelling X
Foundations
Construction X Estimated time of manufacturing eight weeks (see Word 1.)
Roofing X Estimated time of manufacturing 6 weeks (see Word 2.)
Ornament
Sound and Lighting Techniques X Estimated time of manufacturing three weeks (see Word three.)
Inner Furnishings X
Landscaping Workds X
Closing Cleansing X
Testing X
AssignmentTutorOnline
Exercise Commonplace Minimal Most L1 L2 L3 L4
Process Period (weeks) Labour Ranges (males.day)
Web site Levelling 10 5 20 three,000 6,250 18,750 12,500
Foundations 12 6 24 four,500 four,500 9,000 18,000
Construction (manufacturing) zero zero zero zero
Construction (assemblage) 16 eight 32 zero 32,500 eight,000 17,800
Roofing (manufacturing) zero zero zero zero
Roofing (assemblage) eight four 16 zero 12,000 eight,000 zero
Ornament 12 6 24 16,500 24,000 22,500 zero
Sound and Lighting Techniques (manufacturing) zero zero zero zero
Sound and Lighting Techniques (assemblage) 12 6 24 31,500 zero zero zero
Inner Furnishings 12 6 24 zero zero 75,600 21,000
Landscaping Workds eight four 16 2,500 5,000 12,500 16,500
Closing Cleansing eight four 16 zero zero 7,300 four,200
Testing four 2 eight 2,250 zero zero zero
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
four | P a g e
Desk three
Tools allocation and Price
Desk four
Labour Availability
Desk 5
Labour Price (per hour)
Minimal –
Commonplace Commonplace Commonplace –
Most Unit Price
per week
Web site Levelling 1 2 three £125,000
Foundations 2 three four £118,000
Construction (manufacturing)
Construction (assemblage) 2 three four £250,000
Roofing (manufacturing)
Roofing (assemblage) 2 three four £250,000
Ornament
Sound and Lighting Techniques (manufacturing)
Sound and Lighting Techniques (assemblage)
Inner Furnishings 1 2 three £55,000
Landscaping Workds 1 1 2 £80,000
Closing Cleansing
Testing
Tools
London Mumbai Eire
L1 300 500 200
L2 200 400 150
L3 700 600 500
L4 100 300 150
London Mumbai Eire
L1 £25.00 £12.50 £16.67
L2 £20.00 £10.00 £13.33
L3 £17.50 £eight.75 £11.67
L4 £15.00 £7.50 £10.00
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
5 | P a g e
Desk 6
Transportation and
Lodging Price
Desk 7
Extra time Scheme (enhance in hourly price)
Desk eight
Bonus Scheme
Period
London Mumbai £850.00 2 days
Mumbai London £920.00 2 days
London Eire £120.00 1 day
Eire London £150.00 1 day
Lodging Price £25.00/day
Transportation Price
25% As much as three hours
35% three to five hours
50% Greater than 5 hours
100% Weekends
Antecipation
of Ending
Date Bonus
1 Week £1,000,000
2 Week £1,250,000
three Week £1,500,000
four Week £1,750,000
5 Week £2,500,000
6 Week £three,000,000
7 Week £three,500,000
eight Week £four,000,000
9 Week £four,500,000
10 Week £5,000,000
11 Week £5,500,000
12 Week £5,750,000
13 Week £6,000,000
14 Week £6,250,000
15 Week £6,250,000