Week 5 Project
Instructions
MGT3059-Operations Management SU01
Scheduling
For an organization, the following project schedule is given. Assume that all times are in days.
Task Predecessor
Normal
Time
Crash
Time
Crash Cost Slope
(per day)
A None 7 7 NA
B A 3 3 NA
C A 8 4 600
D A 4 4 NA
E B 6 5 600
F C, D 2 2 NA
G E, F 6 6 NA
H F 5 3 400
I G, H 4 4 NA
J I 2 2 NA
Address the following:
Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of
creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF
times.
Calculate the slack time for each activity.
Identify the critical path(s).
Assume that the organization will receive a $400 bonus for each day the duration of the project is
shortened. The organization is also responsible for paying the crash cost associated with shortening the
schedule. To maximize the net profit, identify which task you should crash and by how much.
Submission Details:
Submit your report in a 3- to 4-page Word document, using APA style.
Submit it to the Submissions Area by the due date assigned.
Name your document SUO_MGT3059_W5_ LastName_FirstInitial.doc.
NSG 4410 Population Health Nursing
NSG 4410 Population Health Nursing Instructions for the Healthy People Paper The purpose of this paper is to apply research-based, public health objectives to a selected community aggregate. The Healthy People 2030 website will be used by the students. This assignment is based on the aggregate in the community that they student chooses. The paper […]