Hyde Park Stadium Project
HYDE PARK STADIUM
PROJECT SPECIFICATIONS
MIGUEL DIAS COSTA
Anglia Ruskin College London
2019/2020
This case research was ready by Miguel Dias Costa.
It’s a fictional case research aimed toward serving to college students
perceive the complexities of growing challenge
administration options.
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
1 | P a g e
Hyde Park Stadium
The Mayor of London has determined to approve a proposal to construct a brand new venue to host mega occasions in
Hyde Park. As a result of particular attribute of the challenge and to the positioning restrictions the development has
to comply with some very particular specs. The brand new venue will likely be named Hyde Park Stadium. The challenge
is because of begin in November 1st, 2019 and be accomplished no later than the 2nd of April 2022.
The development will comprehend a number of phases. Among the works will likely be carried out on website and others
will solely include the assemblage of the structural parts and roofing (see Desk 1).
To make sure that there will likely be no useless intervals, these works to be carried out off website should be ordered
and obtained on time.
The overall length of every one of many phases is dependent upon labour to be allotted (see Desk 2). Nonetheless,
the scale of the workforce may even have penalties on the gear to make use of, which implies that prices
associates with every workforce aren’t straight proportional with its measurement (see Desk three).
The requirements of manufacturing for every exercise are introduced in Desk 2.
Work drive for the challenge may be employed both regionally (London) or internationally (Dublin and Mumbai).
The out there workforce is introduced on Desk four.
Labour prices is introduced in Desk 5. The transportation prices is introduced in Desk 6.
Project Constraints:
1. There are three teams of attainable employees to do the works. The unitary value is completely different as every
group represents completely different degree of and a distinct origin by way of location. This
scenario is as a result of lack of extremely certified employees in London.
2. The degrees of qualification of the employees (L1 to L4) doesn’t enable any swap. That’s, a L2 employee
can’t carry out the work of a L1. And the identical applies to L3 and L4.
three. The employees will arrive straight from their house nation sooner or later forward of their working schedule.
The transportation value is supported by the Contractor.
four. The gear wanted is dependent upon the variety of employees and the usual of development (see
Desk three).
5. In the course of the time of labor, all employees will likely be hosted in a resort in London and all bills will likely be
supported by the Contractor.
6. The CEO is conscient of the danger of not having the development concluded earlier than the deadline.
Due to this fact, he has established a bonus for earlier completion of the challenge. This bonus will likely be
awarded to the members of the Project Administration Crew (see Desk eight).
7. All employees are solely allowed to work eight hours per day and 5 days per week. Nonetheless, if at any
additional time is required, the price of the employee will improve in accordance with Desk 7.
Moreover, the next day will likely be taken off as a solution to decrease the workload and guarantee
high quality in development works.
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
2 | P a g e
eight. If any employee is allotted for a interval of lower than eight hours per day nonetheless he/she will likely be paid eight
hours.
9. Time for travelling is paid on the regular price. The variety of days inbound and outbound, as
nicely as its prices, is introduced in Desk 6.
10. All employees will likely be paid in line with the class (see Desk 5).
Questions:
1. Develop the challenge actions and price primarily based on the earlier specs and constraints,
contemplating that:
a. The target is to finish the method with the least attainable value.
b. The target is to finish the challenge throughout the least attainable timing.
c. The target is to make sure that the whole development course of will result in the best
attainable high quality.
2. For every answer it is best to clearly sate your assumptions and choices.
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
three | P a g e
Desk 1
Building Schedule
Notes:
1. Manufacturing time may be shortened by 2 weeks with an additional value of 30% on
primary value).
2. Manufacturing time may be shortened by three weeks with an additional value of 50% on
primary value).
three. Manufacturing time may be shortened by 1 week with an additional value of 70% on primary
value).
Desk 2
Building Requirements
The place:
1. Activity Length: Represents the variety of working days allotted for the duty.
2. Activity Content material: Represents the works to be carried out on that job
three. Activity Predecessors: Characterize the duty that should be accomplished earlier than the duties begins.
four. Labour in Days: Represents the variety of man-days for every job an for every employee degree.
5. Every week will comprehend 5 working days of eight hours. No additional hours or additional days are allowed.
Exercise Website Off Website Remarks
Website Levelling X
Foundations
Construction X Estimated time of manufacturing eight weeks (see Observe 1.)
Roofing X Estimated time of manufacturing 6 weeks (see Observe 2.)
Ornament
Sound and Lighting Programs X Estimated time of manufacturing three weeks (see Observe three.)
Inner Furnishings X
Landscaping Workds X
Last Cleansing X
Testing X
AssignmentTutorOnline
Exercise Commonplace Minimal Most L1 L2 L3 L4
Activity Length (weeks) Labour Ranges (males.day)
Website Levelling 10 5 20 three,000 6,250 18,750 12,500
Foundations 12 6 24 four,500 four,500 9,000 18,000
Construction (manufacturing) zero zero zero zero
Construction (assemblage) 16 eight 32 zero 32,500 eight,000 17,800
Roofing (manufacturing) zero zero zero zero
Roofing (assemblage) eight four 16 zero 12,000 eight,000 zero
Ornament 12 6 24 16,500 24,000 22,500 zero
Sound and Lighting Programs (manufacturing) zero zero zero zero
Sound and Lighting Programs (assemblage) 12 6 24 31,500 zero zero zero
Inner Furnishings 12 6 24 zero zero 75,600 21,000
Landscaping Workds eight four 16 2,500 5,000 12,500 16,500
Last Cleansing eight four 16 zero zero 7,300 four,200
Testing four 2 eight 2,250 zero zero zero
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
four | P a g e
Desk three
Tools allocation and Value
Desk four
Labour Availability
Desk 5
Labour Value (per hour)
Minimal –
Commonplace Commonplace Commonplace –
Most Unit Value
per week
Website Levelling 1 2 three £125,000
Foundations 2 three four £118,000
Construction (manufacturing)
Construction (assemblage) 2 three four £250,000
Roofing (manufacturing)
Roofing (assemblage) 2 three four £250,000
Ornament
Sound and Lighting Programs (manufacturing)
Sound and Lighting Programs (assemblage)
Inner Furnishings 1 2 three £55,000
Landscaping Workds 1 1 2 £80,000
Last Cleansing
Testing
Tools
London Mumbai Eire
L1 300 500 200
L2 200 400 150
L3 700 600 500
L4 100 300 150
London Mumbai Eire
L1 £25.00 £12.50 £16.67
L2 £20.00 £10.00 £13.33
L3 £17.50 £eight.75 £11.67
L4 £15.00 £7.50 £10.00
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
5 | P a g e
Desk 6
Transportation and
Lodging Value
Desk 7
Time beyond regulation Scheme (improve in hourly value)
Desk eight
Bonus Scheme
Length
London Mumbai £850.00 2 days
Mumbai London £920.00 2 days
London Eire £120.00 1 day
Eire London £150.00 1 day
Lodging Value £25.00/day
Transportation Value
25% As much as three hours
35% three to five hours
50% Greater than 5 hours
100% Weekends
Antecipation
of Ending
Date Bonus
1 Week £1,000,000
2 Week £1,250,000
three Week £1,500,000
four Week £1,750,000
5 Week £2,500,000
6 Week £three,000,000
7 Week £three,500,000
eight Week £four,000,000
9 Week £four,500,000
10 Week £5,000,000
11 Week £5,500,000
12 Week £5,750,000
13 Week £6,000,000
14 Week £6,250,000
15 Week £6,250,000