Hyde Park Stadium Project
HYDE PARK STADIUM
PROJECT SPECIFICATIONS
MIGUEL DIAS COSTA
Anglia Ruskin College London
2019/2020
This case examine was ready by Miguel Dias Costa.
It’s a fictional case examine geared toward serving to college students
perceive the complexities of creating mission
administration options.
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
1 | P a g e
Hyde Park Stadium
The Mayor of London has determined to approve a proposal to construct a brand new venue to host mega occasions in
Hyde Park. Because of the particular attribute of the mission and to the positioning restrictions the development has
to comply with some very particular specs. The brand new venue might be named Hyde Park Stadium. The mission
is because of begin in November 1st, 2019 and be accomplished no later than the 2nd of April 2022.
The development will comprehend a number of phases. Among the works might be carried out on web site and others
will solely include the assemblage of the structural parts and roofing (see Desk 1).
To make sure that there might be no lifeless durations, these works to be carried out off web site have to be ordered
and acquired on time.
The full period of every one of many phases depends upon labour to be allotted (see Desk 2). Nonetheless,
the dimensions of the group can even have penalties on the gear to make use of, which implies that prices
associates with every group aren’t instantly proportional with its measurement (see Desk three).
The requirements of manufacturing for every exercise are offered in Desk 2.
Work drive for the mission might be employed both domestically (London) or internationally (Dublin and Mumbai).
The obtainable workforce is offered on Desk four.
Labour prices is offered in Desk 5. The transportation prices is offered in Desk 6.
Project Constraints:
1. There are three teams of attainable employees to do the works. The unitary price is totally different as every
group represents totally different degree of and a special origin when it comes to location. This
state of affairs is as a result of lack of extremely certified employees in London.
2. The degrees of qualification of the employees (L1 to L4) doesn’t permit any swap. That’s, a L2 employee
can’t carry out the work of a L1. And the identical applies to L3 and L4.
three. The employees will arrive instantly from their house nation at some point forward of their working schedule.
The transportation price is supported by the Contractor.
four. The gear wanted depends upon the variety of employees and the usual of development (see
Desk three).
5. In the course of the time of labor, all employees might be hosted in a lodge in London and all bills might be
supported by the Contractor.
6. The CEO is conscient of the danger of not having the development concluded earlier than the deadline.
Due to this fact, he has established a bonus for earlier completion of the mission. This bonus might be
awarded to the members of the Project Administration Crew (see Desk eight).
7. All employees are solely allowed to work eight hours per day and 5 days per week. Nonetheless, if at any
time beyond regulation is required, the price of the employee will enhance in accordance with Desk 7.
Moreover, the next day might be taken off as a method to decrease the workload and guarantee
high quality in development works.
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
2 | P a g e
eight. If any employee is allotted for a interval of lower than eight hours per day nonetheless he/she might be paid eight
hours.
9. Time for travelling is paid on the regular charge. The variety of days inbound and outbound, as
properly as its prices, is offered in Desk 6.
10. All employees might be paid in line with the class (see Desk 5).
Questions:
1. Develop the mission actions and value based mostly on the earlier specs and constraints,
contemplating that:
a. The target is to finish the method with the least attainable price.
b. The target is to finish the mission throughout the least attainable timing.
c. The target is to make sure that your entire development course of will result in the best
attainable high quality.
2. For every resolution it’s best to clearly sate your assumptions and selections.
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
three | P a g e
Desk 1
Development Schedule
Notes:
1. Manufacturing time might be shortened by 2 weeks with an additional price of 30% on
primary price).
2. Manufacturing time might be shortened by three weeks with an additional price of 50% on
primary price).
three. Manufacturing time might be shortened by 1 week with an additional price of 70% on primary
price).
Desk 2
Development Requirements
The place:
1. Activity Length: Represents the variety of working days allotted for the duty.
2. Activity Content material: Represents the works to be carried out on that activity
three. Activity Predecessors: Signify the duty that need to be accomplished earlier than the duties begins.
four. Labour in Days: Represents the variety of man-days for every activity an for every employee degree.
5. Every week will comprehend 5 working days of eight hours. No further hours or further days are allowed.
Exercise Website Off Website Remarks
Website Levelling X
Foundations
Construction X Estimated time of manufacturing eight weeks (see Be aware 1.)
Roofing X Estimated time of manufacturing 6 weeks (see Be aware 2.)
Ornament
Sound and Lighting Programs X Estimated time of manufacturing three weeks (see Be aware three.)
Inside Furnishings X
Landscaping Workds X
Ultimate Cleansing X
Testing X
AssignmentTutorOnline
Exercise Customary Minimal Most L1 L2 L3 L4
Activity Length (weeks) Labour Ranges (males.day)
Website Levelling 10 5 20 three,000 6,250 18,750 12,500
Foundations 12 6 24 four,500 four,500 9,000 18,000
Construction (manufacturing) zero zero zero zero
Construction (assemblage) 16 eight 32 zero 32,500 eight,000 17,800
Roofing (manufacturing) zero zero zero zero
Roofing (assemblage) eight four 16 zero 12,000 eight,000 zero
Ornament 12 6 24 16,500 24,000 22,500 zero
Sound and Lighting Programs (manufacturing) zero zero zero zero
Sound and Lighting Programs (assemblage) 12 6 24 31,500 zero zero zero
Inside Furnishings 12 6 24 zero zero 75,600 21,000
Landscaping Workds eight four 16 2,500 5,000 12,500 16,500
Ultimate Cleansing eight four 16 zero zero 7,300 four,200
Testing four 2 eight 2,250 zero zero zero
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
four | P a g e
Desk three
Gear allocation and Price
Desk four
Labour Availability
Desk 5
Labour Price (per hour)
Minimal –
Customary Customary Customary –
Most Unit Price
per week
Website Levelling 1 2 three £125,000
Foundations 2 three four £118,000
Construction (manufacturing)
Construction (assemblage) 2 three four £250,000
Roofing (manufacturing)
Roofing (assemblage) 2 three four £250,000
Ornament
Sound and Lighting Programs (manufacturing)
Sound and Lighting Programs (assemblage)
Inside Furnishings 1 2 three £55,000
Landscaping Workds 1 1 2 £80,000
Ultimate Cleansing
Testing
Gear
London Mumbai Eire
L1 300 500 200
L2 200 400 150
L3 700 600 500
L4 100 300 150
London Mumbai Eire
L1 £25.00 £12.50 £16.67
L2 £20.00 £10.00 £13.33
L3 £17.50 £eight.75 £11.67
L4 £15.00 £7.50 £10.00
Hyde Park Stadium Project Specs
© Copyright Miguel Dias Costa, 2019
5 | P a g e
Desk 6
Transportation and
Lodging Price
Desk 7
Additional time Scheme (enhance in hourly price)
Desk eight
Bonus Scheme
Length
London Mumbai £850.00 2 days
Mumbai London £920.00 2 days
London Eire £120.00 1 day
Eire London £150.00 1 day
Lodging Price £25.00/day
Transportation Price
25% As much as three hours
35% three to five hours
50% Greater than 5 hours
100% Weekends
Antecipation
of Ending
Date Bonus
1 Week £1,000,000
2 Week £1,250,000
three Week £1,500,000
four Week £1,750,000
5 Week £2,500,000
6 Week £three,000,000
7 Week £three,500,000
eight Week £four,000,000
9 Week £four,500,000
10 Week £5,000,000
11 Week £5,500,000
12 Week £5,750,000
13 Week £6,000,000
14 Week £6,250,000
15 Week £6,250,000