IT Project
This venture simulates the Assessment and Planning wanted to offer IT providers for a brand new constructing. The scholar
should submit a Project Schedule based mostly on the Project Necessities and particulars beneath.
1. Utilizing the connected MS Phrase desk template, create a venture schedule. The venture schedule will want
the next columns: WBS; Activity #; Activity Motion; Period; Predecessor; and Sources.
2. Don’t transcend the scope recognized beneath. The venture solely covers duties recognized beneath.
Background: IT has been notified that a new workplace constructing is prepared for occupancy. All telecommunication
cables are in place. Rooms are geared up to offer entry to the community as soon as the community servers are
put in. Wi-fi routers are put in all through the constructing to offer wi-fi entry as soon as the community
servers are put in. VOIP telephones and vendor-supplied networked copier are already ordered.
NOTE: be aware specs could include a number of actions/duties. Break them down into separate rows and group
comparable actions right into a block of duties (i.e., Buy Sources; Setup Tools; and so forth.).
Project Specs:
• Buy, setup, deploy and check community servers that can be managed within the new constructing’s IT space.
o Setup contains loading and testing community software program at company IT earlier than deployment.
o Take a look at community servers within the new constructing after deployment.
o NOTE: Community servers should be put in and operational earlier than different gadgets might be examined
for web and wi-fi connectivity.
• Buy, setup, deploy and check Desktop PCs and Laptops in places of work, labs and administrative areas.
o Setup contains loading and testing company software program at company IT earlier than deployment.
o Take a look at all programs and guarantee they’ll entry the community as soon as deployed.
o Take a look at all wi-fi programs and guarantee they’ll entry the wi-fi routers.
• Buy, deploy and check wi-fi Projectors.
o Take a look at all Projectors to make sure desktops can entry them through direct cabling.
o Take a look at all Project to make sure cell laptops can entry them wirelessly.
• Buy, deploy and check VOIP telephones (they use the community to obtain/generate telephone calls).
o Take a look at all telephones to make sure they perform correctly throughout the community.
• Take a look at networked Printers/Copiers as soon as they’re delivered by the lease vendor.
o Take a look at all printers/copiers to make sure they’ll print paperwork despatched throughout the community.
The COO has decided the next guidelines to facilitate occupancy:
• IT Space should be prepared first. Deploy and check community servers and desktop PC three weeks earlier than any
different location.
• Administrative Areas should be prepared second. Deploy and check their desktop PCs and VOIP telephones one
week earlier than remaining places.
• Convention & Assembly Rooms should be prepared third. Deploy and check their desktop PCs, VOIP
telephones and wi-fi projectors 5 days earlier than the remaining places.
• Places of work and labs are final. Deploy and check their desktop PCs, VOIP telephones and wi-fi projectors
earlier than occupancy.
Project Particulars: The brand new constructing contains the IT Space, Laptop Labs, Administrative Areas, Particular person
Places of work, a Convention Room, and a Public Assembly Room.
IT Space: sources embody
• four community servers
• 1 desktop PC
• 2 laptops
• 2 VOIP telephones
Administrative Areas: 2 administrative areas will every have
• four workstations, every with a desktop PC, networked through a community port
• a VOIP telephone for every of the four workstations
• a vendor-supplied networked copier
Convention Room. The convention room has
• a wi-fi ceiling-mounted Projector
• community connectivity through a community cable and a wi-fi entry level
• a VOIP telephone
Assembly Room. The assembly room has
• a wi-fi ceiling-mounted Projector
• 1 desktop PC with community connectivity through a community cable.
• 2 VOIP telephones (one close to the lectern and the opposite wall mounted on the entrance
Particular person Places of work: 40 places of work will every have
• a desktop PC networked through a community port
• a VOIP telephone
Laptop Labs: 2 pc labs will every have
• a wi-fi ceiling-mounted Projector
• a desktop PC, networked through a community port, and straight cabled to the Projector
• 25 desktop PCs networked through a community port
• a VOIP telephone
• a vendor-supplied networked copier
Personnel Assignments
PC Specialist (tools buy, software program setup and PC Help):
o buy, setup and set up of recent laptops and desktop computer systems and company software program
o buy of all projectors
o work with Community Specialist to make sure community entry is accessible on all computer systems and
networked printers
Community Specialist (Telecomm Help):
o setup and set up of community servers and all VOIP telephones
o work with PC Specialist to make sure community entry is accessible on all computer systems and networked
printers
AV Specialist (A/V necessities):
o Set up of all wi-fi projectors
o work with PC Specialist to make sure projectors might be accessed by acceptable computer systems
Take time to consider how the work of the Specialists can be carried out.
• Perceive how the occupancy guidelines have an effect on the schedule timeline.
o Since some places are occupied at completely different occasions, deal with the deployment and testing of
sources for every location individually (i.e. IT Space separate from Admin Space; Convention Room,
Assembly Room, and so forth.).
• Ensure you fulfill all venture specs.
• The PC Specialist, Community Specialist and AV Specialist might be finishing duties concurrently and it’s fairly
attainable that one specialist must wait whereas one other specialist completes a activity.
• The schedule should embody a milestone for every block of duties (Buy Sources, Setup Tools,
Deploy and Take a look at).
o Every useful resource (community servers, computer systems, projectors) should be bought individually since
they may come from completely different distributors. The VOIP telephones and third-party community printers are
already ordered and simply should be examined as soon as they arrive.
o Be aware: a single activity could also be used for a useful resource that’s examined at a selected time (i.e. the testing of
all computer systems for administrative areas is usually a single activity; or the testing of all pc for the
2 pc labs is usually a single activity). Nonetheless, a single activity can’t be used when an motion
should be accomplished throughout completely different occupancy durations (i.e., testing of IT Space sources is a separate
activity from testing of Administrative Areas, and so forth. since they take occupancy at completely different occasions.)
• Activity Actions should begin with a verb and describe the motion (i.e., Take a look at VOIP telephones)
o Milestones don’t begin with verbs and have a zero length.
• When creating the schedule, use your finest guess in figuring out Period. Use a single measure (i.e.,
min.) for all duties.
• Sources should embody each the individuals (title of the IT Specialist) and particular useful resource(s).
• When creating Predecessors, level to the respective Activity # (not the WBS quantity). It’s not obligatory
to incorporate a activity that’s already a predecessor of one other activity (i.e. take into account the next duties: 1:
Order meals, 2: Eat meals, three: Cleanup. The predecessor for two is 1. The predecessor for three is 2 (i.e. 2
already has a predecessor of 1).
o Be aware: watch out about predecessors. Not solely are they straight associated to the duties that
proceed them inside a Milestone however they could be straight associated to duties inside different
Milestones (instance: community servers should be operational earlier than different tools might be
examined for community connectivity – search for different dependencies described above).
• The WBS must be accomplished as soon as the schedule is in its remaining model.

—-

IT Initiative
This venture simulates the Assessment and planning required to ship data know-how providers for a brand new constructing. The pupil

should present a Project Schedule based mostly on the Project Necessities and specs listed beneath

1. Create a venture schedule utilizing the connected MS Phrase desk template. The venture timetable will necessitate

WBS; Activity #; Activity Motion; Period; Predecessor; and Sources are the columns.

2. Don’t deviate from the scope outlined right here. The venture solely addresses the duties listed beneath.

The IT division has been suggested that a new workplace facility is prepared for occupancy. Telecommunications generally

The cables have been put in. As soon as the community servers are operational, the rooms are outfitted to allow community entry.

put in. Wi-fi routers are put in all through the constructing to offer wi-fi entry as soon as the